Cabinet
has given the Ministry of Petroleum up to March, next year, to connect
the Atuabo Gas pipeline in the Western Region to the West Africa Gas
Pipeline (WAGP) to enable reverse flow of gas between the two lines.
The
six months ultimatum follows an approval from the highest policy
decision body of the government to the ministry to continue with
processes aimed at connecting the two gas pipelines which are central to
the production of adequate electricity in the country.
The
approval marks an important milestone in efforts by the ministry to
ensure that the Kpone Thermal Plant and the other thermal plants at the
power enclave near Tema are not deprived of gas for electricity
generation whenever the West Africa Gas Company Limited (WAPCo) reduces
gas supplies from Nigeria to them.
Consequently, the Chief
Director of the Petroleum Ministry, Prof. Thomas Akabzaa, said the
ministry was now facilitating negotiations between the Ghana Gas and
WAPCo on how the interconnection should be carried out.
“Technically,
both have agreed that Ghana Gas will construct the pipeline from their
end to the West Africa Gas Pipeline portion so that they (WAPCo) will
also construct from there to their end for the connectivity to
materialise,” Prof. Akabzaa said.
Beyond servicing the Kpone
Plant, the gas from the Atuabo Processing Plant would also help serve
the fuel needs of some of the plants at the Kpone Power enclave,
majority of which have retrofitted their plants to run on gas as well as
crude.
Once discussions on the modalities of the project are
firmed up, the chief director said the two sides would proceed to talk
about tariffs which would be based on the general framework of tariffs
currently used in the sub-region.
Selecting contractor
The
distance between the Ghana Gas and WAPCo portion is about 1.5
kilometres and its successful connection will mean that gas can flow
from the east of the pipeline to the west and vice versa, thereby
bringing consistency to gas supplies to the Kpone Plant.
The
plant accounts for about 220 megawatts of the country's electricity
needs and has been at the mercy of the erratic gas flows from the WAGP.
Gas from the WAGP has been inconsistent ever since the pipeline was
inaugurated.
Those inconsistencies force the Kpone Plant to shut
down intermittently for lack of gas or revert to crude which is
comparatively costly to run . The result has been a decline in
national electricity generation, translating into the rationing of power
to industrial and domestic consumers.
Although signals from
Ghana Gas showed that it would want to engage Sinopec, the contractor
working on the Atuabo Gas Plant to construct the 1.5 kilometre pipeline
to the WAPCo section, the chief director said the ministry had requested
that a procurement process be undertaken to allow that to happen.
“So
we have asked them to ensure that the procurement processes are
cleared. WAPCo will be doing it themselves; they have internal engineers
and contractors,” the Prof. Akabzaa added.
Additional pipeline
Prof.
Akabzaa explained that investment costs on the project were to be
recouped from the revenues to be made from the gas retails, and added
that those revenues would be shared based on the cost incurred in
connecting the two sides to the intersection.
“Besides the
reverse flow project, we are looking at ultimately getting a dedicated
pipeline that will run from the west to Tema such that even if the WAGP
has challenges, you will have another pipeline. “The immediate thing is, we do not have enough gas to take up that project,” Prof. Akabzaa said. |
|
|
|
|
No comments:
Post a Comment